H-EMS Pre-Commissioning Plan


Pre-commissioning is the essential first step in delivering a fully operational Building Energy Management System (BEMS). This phase focuses on ensuring that all systems are installed correctly, physically ready for commissioning, and meet design and regulatory requirements. Below is the detailed pre-commissioning plan.

 

1. Objectives

 

  • ​Verify that all equipment, cabling, and infrastructure are installed as per design specifications
  • Confirm that all systems are operational and free from physical defects.
  • Document and resolve installation issues to avoid delays during commissioning.
  • Provide a clear handover point from installation to functional testing.

 

2. Responsibilities

 

  • Mechanical Contractor: Complete installation of HVAC equipment, pipework, ductwork, valves, and dampers. Ensure system balancing.
  • Electrical Contractor: Verify electrical wiring, terminations, and power supply to all BEMS components.
  • BEMS ContractorInspect and conduct pre-functional tests on control panels, sensors, actuators, and field devices.

 

 

3. Pre-Commissioning Activities

 

3.1 Documentation Review

  • Confirm that the following documents are available, accurate, and complete:
  • Wiring diagrams, schematics, and as-built drawings.
  • Control sequences and functional descriptions.
  • Initial draft of the O&M manual, including equipment specifications.
  • Manufacturer’s installation guidelines and data sheets for field devices.

 

3.2 Installation Verification


1. Control Panels:

  • Check panels for proper assembly, labeling, and wiring.
  • Ensure all terminations are secure and correspond to the wiring diagram.
  • Confirm that all circuit breakers, relays, and fuses are correctly installed.


2. Sensors and Actuators:

  • Verify that sensors (temperature, pressure, flow) are installed in the correct locations and free from physical damage.
  • Confirm actuators (valves, dampers) are mounted securely and accessible for maintenance.


3. Cabling and Containment:

  • Inspect cable runs for physical damage, proper containment, and secure fixings.
  • Verify that cable labels match the wiring diagrams and are legible.


4. Power Supply:

  • Check all power supplies for correct voltage and load capacity.
  • Ensure emergency power systems, if applicable, are functional.

 

3.3 Mechanical System Checks


1. Pipework and Ductwork:

  • Confirm that pressure testing, flushing, and cleaning are completed for pipework.
  • Inspect ductwork for leaks, proper insulation, and correct installation.


2. Balancing:

  • Verify that system balancing for air and water flows has been completed by the mechanical contractor.
  • Obtain written confirmation or balancing reports before proceeding.


3. Valves and Dampers:

  • Ensure all control valves and dampers are installed and operate freely.
  • Verify that valve actuators are aligned and securely mounted.

 

3.4 Pre-Functional Testing

 

1. Electrical Testing:

  • Conduct continuity testing to verify all circuits are correctly terminated.
  • Perform earth bonding tests to confirm proper grounding for all panels and equipment.
  • Power on all devices to ensure they operate within specified parameters.

 

2. Communication Testing:

  • Test communication between controllers, sensors, actuators, and the central BEMS.
  • Verify device addressing and protocol compliance (e.g., BACnet, Modbus).
  • Resolve any network conflicts or communication errors.


3. Sensor and Actuator Calibration:

  • Verify that sensors are calibrated and provide accurate readings.
  • Check that actuators move through their full range and respond to manual commands.

 

3.5 Safety Checks

  • Ensure safety-critical systems are installed and functional, including:
  • Fire dampers and smoke extraction systems.
  • Emergency shutdown systems.
  • Pressure relief devices for pipework.

 

4. Deliverables

 

  • Installation Verification Reports: Detailed reports confirming that all systems meet installation requirements.
  • Pre-Functional Test Records: Records of electrical tests, communication checks, and device calibrations.
  • Issue Log: A log of identified issues, including status (resolved or pending), actions taken, and responsible parties.
  • System Readiness Certificate: A formal declaration confirming that systems are ready for commissioning.

 

5. Common Challenges and Solutions

 

  • Incomplete installation: Require signed confirmation from contractors that all installations are complete.
  • Communication errorsTest network configurations early to identify and resolve addressing or protocol issues.
  • Inaccessible sensors or equipment: Coordinate with contractors to ensure all devices are accessible for testing and maintenance.
  • Delays in balancing: Make system balancing a prerequisite before pre-commissioning begins.

 

6. Benefits of a Robust Pre-Commissioning Plan

 

  • Saves Time: Resolves installation issues before commissioning, preventing delays.
  • Improves Accuracy: Ensures systems are physically ready for functional testing.
  • Reduces Costs: Identifies and rectifies faults early, avoiding rework during commissioning.
  • Ensures Compliance: Confirms adherence to design specifications and industry standards.

 

Conclusion

 

A detailed pre-commissioning plan ensures that the BEMS and associated systems are physically ready for commissioning, meeting design and regulatory requirements. By verifying installations, resolving issues, and documenting readiness, pre-commissioning lays the groundwork for a smooth and successful commissioning phase. 